Dept. of Trans. PROGRESS Serial No. Contract No. 11-168-14-28 03-1E1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 58% 03-BUT-70-14.8/ .0 Federal Project: NHBH-X007(9) Progress payment No. 05 Payment period ending: 06-16-11 BUGLER CONSTRUCTION 4847 HOPYARD RD SUITE 4 NO 39 PLEASANTON CA 94588 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 692,374.20 152,734.20 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 692,374.20 152,734.20 5. Mobilization 70,000.00 0.00 6. Total Work Completed 762,374.20 7. Deductions 0.00 5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 762,374.20 157,734.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 157,734.20