Dept. of Trans. PROGRESS Serial No. Contract No. 09-238-10-21 03-1E1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 6% 03-COL-5-R2.0/R32.9 Federal Project: ACHS-000C(302) IMG-000C(302) Progress payment No. 01 Payment period ending: 08-20-09 MIDSTATE BARRIER INC P O BOX 30550 STOCKTON CA 952130550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 147,791.25 147,791.25 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 147,791.25 147,791.25 5. Mobilization 15,000.00 15,000.00 6. Total Work Completed 162,791.25 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 162,791.25 162,791.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 162,791.25