Dept. of Trans. PROGRESS Serial No. Contract No. 09-264-13-12 03-1E1304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 28% 21% 03-COL-5-R2.0/R32.9 Federal Project: ACHS-000C(302) IMG-000C(302) Progress payment No. 02 Payment period ending: 09-17-09 MIDSTATE BARRIER INC P O BOX 30550 STOCKTON CA 952130550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 716,732.51 568,941.26 2.a. Extra Work 16,578.32 16,578.32 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 733,310.83 585,519.58 5. Mobilization 28,500.00 13,500.00 6. Total Work Completed 761,810.83 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 761,810.83 599,019.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 599,019.58