Dept. of Trans. SEMI-FINAL Serial No. Contract No. 07-003-16-30 03-1E1504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-193-5.6/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 09-26-06 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,223.50 0.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 193,223.50 0.00 5. Mobilization 6. Total Work Completed 193,223.50 7. Deductions -1,275.00 10,000.00 8. a.Contract Retentions -9,023.68 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9,023.68 0.00 9. Total pay to Contractor 191,948.50 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00