Dept. of Trans. PROGRESS Serial No. Contract No. 08-238-09-44 03-1E1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 54% 03-BUT-70-10.9/11.7 Federal Project: ACST-P070(93) PH-P070(93) STPL-6203(23) Progress payment No. 06 Payment period ending: 08-20-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,320,774.49 824,602.64 2.a. Extra Work 33,826.33 0.00 b. Adjustment Comp. 41,400.00 -3,600.00 3. Materials on Hand 0.00 -45,304.00 4. Earned Subject to Retention 3,396,000.82 775,698.64 5. Mobilization 274,825.00 0.00 6. Total Work Completed 3,670,825.82 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,650,825.82 765,698.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 765,698.64