Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-339-13-06 03-1E1604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-BUT-70-10.9/11.7 Federal Project: ACST-P070(93) PH-P070(93) STPL-6203(23) Progress payment No. 09 Payment period ending: 11-06-08 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,669,374.20 40,375.00 2.a. Extra Work 100,121.14 13,697.83 b. Adjustment Comp. 151,082.63 -19,444.94 3. Materials on Hand 4. Earned Subject to Retention 3,920,577.97 34,627.89 5. Mobilization 274,825.00 0.00 6. Total Work Completed 4,195,402.97 7. Deductions -30,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,165,402.97 24,627.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 24,627.89