Dept. of Trans. SEMI-FINAL Serial No. Contract No. 08-158-14-43 03-1E5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-160-5.8/ .0 Federal Project: NONE Progress payment No. 07 Payment period ending: 03-21-08 AMERICAN CIVIL CONSTRUCTORS WEST COAST INC 3701 MALLARD DRIVE BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 566,340.50 13,704.52 2.a. Extra Work 129,488.02 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 695,828.52 13,704.52 5. Mobilization 40,000.00 0.00 6. Total Work Completed 735,828.52 7. Deductions -7,000.00 0.00 8. a.Contract Retentions -24,539.75 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 24,539.75 0.00 9. Total pay to Contractor 728,828.52 13,704.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,704.52