Dept. of Trans. PROGRESS Serial No. Contract No. 13-234-08-41 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 14% 12% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 04 Payment period ending: 08-20-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 519,806.25 401,285.75 2.a. Extra Work 24,253.52 5,915.52 b. Adjustment Comp. 1,669.62 1,084.19 3. Materials on Hand 4. Earned Subject to Retention 545,729.39 408,285.46 5. Mobilization 312,500.00 312,500.00 6. Total Work Completed 858,229.39 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 858,229.39 720,785.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 720,785.46