Dept. of Trans. PROGRESS Serial No. Contract No. 13-326-10-30 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 38% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 07 Payment period ending: 11-19-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,829,863.00 655,876.40 2.a. Extra Work 29,220.21 0.00 b. Adjustment Comp. -147,919.75 -152,265.00 3. Materials on Hand 0.00 -88,404.91 4. Earned Subject to Retention 2,711,163.46 415,206.49 5. Mobilization 593,750.00 0.00 6. Total Work Completed 3,304,913.46 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,304,913.46 415,206.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 415,206.49