Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 13-338-08-49 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 54% 38% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 08 Payment period ending: 11-19-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,829,863.00 0.00 2.a. Extra Work 29,220.21 0.00 b. Adjustment Comp. -147,919.75 0.00 3. Materials on Hand 236,880.37 236,880.37 4. Earned Subject to Retention 2,948,043.83 236,880.37 5. Mobilization 593,750.00 0.00 6. Total Work Completed 3,304,913.46 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,541,793.83 236,880.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 236,880.37