Dept. of Trans. PROGRESS Serial No. Contract No. 13-353-09-12 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 45% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 09 Payment period ending: 12-18-13 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,886,859.27 1,056,996.27 2.a. Extra Work 29,220.21 0.00 b. Adjustment Comp. -124,386.82 23,532.93 3. Materials on Hand 61,971.07 -174,909.30 4. Earned Subject to Retention 3,853,663.73 905,619.90 5. Mobilization 625,000.00 31,250.00 6. Total Work Completed 4,416,692.66 7. Deductions -1,783.70 -1,783.70 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,476,880.03 935,086.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 935,086.20