Dept. of Trans. PROGRESS Serial No. Contract No. 14-022-09-27 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 54% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 10 Payment period ending: 01-17-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,199,814.37 312,955.10 2.a. Extra Work 36,470.25 7,250.04 b. Adjustment Comp. -124,304.14 82.68 3. Materials on Hand 37,182.64 -24,788.43 4. Earned Subject to Retention 4,149,163.12 295,499.39 5. Mobilization 625,000.00 0.00 6. Total Work Completed 4,736,980.48 7. Deductions -1,783.70 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,772,379.42 295,499.39 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 295,499.39