Dept. of Trans. PROGRESS Serial No. Contract No. 14-055-09-36 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 62% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 11 Payment period ending: 02-20-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,279,815.38 80,001.01 2.a. Extra Work 36,470.25 0.00 b. Adjustment Comp. -124,304.14 0.00 3. Materials on Hand 0.00 -37,182.64 4. Earned Subject to Retention 4,191,981.49 42,818.37 5. Mobilization 625,000.00 0.00 6. Total Work Completed 4,816,981.49 7. Deductions -1,783.70 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,815,197.79 42,818.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 42,818.37