Dept. of Trans. PROGRESS Serial No. Contract No. 14-112-14-10 03-1E5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 75% 03-BUT-70-28.2/ .0 Federal Project: ACST-P070(103) PBH-P070(103) Progress payment No. 14 Payment period ending: 04-17-14 GOLDEN STATE BRIDGE INC 2990 BAY VISTA COURT #D BENICIA CA 94510 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,216,854.96 248,026.64 2.a. Extra Work 36,470.25 0.00 b. Adjustment Comp. -86,816.47 37,487.67 3. Materials on Hand 4. Earned Subject to Retention 5,166,508.74 285,514.31 5. Mobilization 625,000.00 0.00 6. Total Work Completed 5,791,508.74 7. Deductions -1,783.70 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 5,789,725.04 285,514.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 285,514.31