Dept. of Trans. PROGRESS Serial No. Contract No. 12-020-12-56 03-1E6704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 60% 03-SAC-99-0.1/12.0 Federal Project: NH-P099(531) Progress payment No. 10 Payment period ending: 01-19-12 TEICHERT CONSTRUCTION 4401 DULUTH AVE ROSEVILLE, CA 95678 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,429,446.66 0.00 2.a. Extra Work 225,441.72 3,763.83 b. Adjustment Comp. 1,377.20 0.00 3. Materials on Hand 105,077.13 105,077.13 4. Earned Subject to Retention 8,761,342.71 108,840.96 5. Mobilization 682,000.00 0.00 6. Total Work Completed 9,338,265.58 7. Deductions -4,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 9,439,342.71 108,840.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 108,840.96