Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 07-303-15-15 03-1E6804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-51-1.0/5.1 Federal Project: NONE Progress payment No. 08 Payment period ending: 09-20-07 MARTIN BROTHERS CONSTRUCTION 20 LIGHT SKY COURT SACRAMENTO CA 95828 Escrow No. 02278 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,299,362.30 44,000.00 2.a. Extra Work 73,528.70 0.00 b. Adjustment Comp. 49,051.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,421,942.00 44,000.00 5. Mobilization 85,000.00 0.00 6. Total Work Completed 3,506,942.00 7. Deductions -76,000.00 -56,000.00 8. a.Contract Retentions -168,897.10 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 168,897.10 168,897.10 9. Total pay to Contractor 3,430,942.00 156,897.10 10. Reduction Amt to Escrow -168,890.00 -168,890.00 11. Payment to Escrow 168,890.00 12. Net Pymt. this Estimate -11,992.90