Dept. of Trans. PROGRESS Serial No. Contract No. 07-113-11-05 03-1E7204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 2% 0% 03-SAC-5-25.4/34.3 Federal Project: MTCE Progress payment No. 02 Payment period ending: 04-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 125,287.50 121,350.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 125,287.50 121,350.00 5. Mobilization 6. Total Work Completed 125,287.50 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions -12,528.75 -12,135.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 107,758.75 104,215.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 104,215.00