Dept. of Trans. PROGRESS Serial No. Contract No. 11-265-08-06 03-1F0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 79% 63% 03-BUT-99-36.3/45.9 Federal Project: HSIN-G000(C34) Progress payment No. 02 Payment period ending: 09-20-11 TRAFFIC SOLUTIONS INC 8490 HARTMEYAER LANE REDDING CA 96002 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 193,604.16 183,760.36 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 193,604.16 183,760.36 5. Mobilization 6. Total Work Completed 193,604.16 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 193,604.16 183,760.36 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 183,760.36