Dept. of Trans. SEMI-FINAL Serial No. Contract No. 19-269-11-16 03-1F2304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-VAR ACIM-080-3(245) Progress payment No. 009 Payment period ending: 08-13-19 GRANITE ROCK COMPANY 5225 HELLYER AVENUE #220 SAN JOSE CA 95138 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,594,580.47 38,038.55 2. a. Extra Work 90,090.17 38,173.28 b. Adustment Comp. -899.38 -899.38 3. Materials on Hand 4. Earned Subject to Retention 3,683,771.26 75,312.45 5. Mobilization 390,000.00 0.00 6. Total Work Completed 4,073,771.26 7. Deductions -14,000.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,059,771.26 85,312.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 85,312.45