Dept. of Trans. PROGRESS Serial No. Contract No. 16-117-07-52 03-1F2604 PROGRESS PAYMENT VOUCHER %complete: %time: 1% 0% Location: Federal Project: 03-SIE-89-0.0/2.3 HSST-P P089-113 Progress payment No. 001 Payment period ending: 04-20-16 MEYERS EARTHWORK INC PO BOX 493730 REDDING CA 960493730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,050.00 13,050.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 13,050.00 13,050.00 5. Mobilization 6. Total Work Completed 13,050.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,050.00 13,050.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,050.00