Dept. of Trans. PROGRESS Serial No. Contract No. 14-147-09-11 03-1F3304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 54% 03-ED-193-18.6/18.7 Federal Project: SSTP-S193(10) Progress payment No. 03 Payment period ending: 05-21-14 DOUG VEERKAMP GENERAL ENGINEERING INC 2585 COLD SPRINGS ROAD PLACERVILLE CA 95667 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 259,476.04 221,143.54 2.a. Extra Work 22,300.55 22,300.55 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 281,776.59 243,444.09 5. Mobilization 20,150.00 5,037.50 6. Total Work Completed 301,926.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 301,926.59 248,481.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 248,481.59