Dept. of Trans. PROGRESS Serial No. Contract No. 18-138-11-47 03-1F4004 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 61% Location: Federal Project: 03-PLA-80-35.1/38.0 NHIM-D 0804-194 Progress payment No. 024 Payment period ending: 05-20-18 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,150,989.13 777,725.19 2. a. Extra Work 707,697.20 53,521.37 b. Adustment Comp. -9,500.00 0.00 3. Materials on Hand 98,410.00 0.00 4. Earned Subject to Retention 24,947,596.33 831,246.56 5. Mobilization 3,206,000.00 0.00 6. Total Work Completed 28,055,186.33 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 28,153,596.33 831,246.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 831,246.56