Dept. of Trans. PROGRESS Serial No. Contract No. 11-234-13-10 03-1F4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 10% 10% 03-SAC-80-5.2/ .0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-19-11 P N P CONSTRUCTION INC 13620 LINCOLN WAY #325 AUBURN CA 95603 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,552.59 58,316.29 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 101,552.59 58,316.29 5. Mobilization 6. Total Work Completed 101,552.59 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 101,552.59 58,316.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 58,316.29