Dept. of Trans. PROGRESS Serial No. Contract No. 12-172-10-26 03-1F4304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 94% 03-SAC-80-5.2/ .0 Federal Project: NONE Progress payment No. 12 Payment period ending: 06-14-12 P N P CONSTRUCTION INC 13620 LINCOLN WAY #325 AUBURN CA 95603 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,056,615.82 19,021.79 2.a. Extra Work 54,167.24 45,688.58 b. Adjustment Comp. -18,211.00 -18,211.00 3. Materials on Hand 4. Earned Subject to Retention 1,092,572.06 46,499.37 5. Mobilization 6. Total Work Completed 1,092,572.06 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,092,572.06 46,499.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 46,499.37