Dept. of Trans. PROGRESS Serial No. Contract No. 11-298-10-39 03-1F5004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 37% 80% 03-SUT-99-T30.6/R32.7 Federal Project: STP-P099(536) Progress payment No. 06 Payment period ending: 10-20-11 ELITE LANDSCAPING INC 2972 LARKIN AVENUE CLOVIS CA 93612 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 471,845.95 106,995.90 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 185,500.00 185,500.00 4. Earned Subject to Retention 657,345.95 292,495.90 5. Mobilization 95,387.60 0.00 6. Total Work Completed 567,233.55 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 752,733.55 292,495.90 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 292,495.90