Dept. of Trans. PROGRESS Serial No. Contract No. 14-234-09-39 03-1F9104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 97% 03-NEV-49-4.3/4.8 Federal Project: STP-P049(156) Progress payment No. 05 Payment period ending: 08-20-14 HANSEN BROS ENTERPRISES P O BOX 1599 GRASS VALLEY CA 95945 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 729,242.56 81,513.05 2.a. Extra Work 149,463.25 149,463.25 b. Adjustment Comp. 22,532.00 17,420.00 3. Materials on Hand 4. Earned Subject to Retention 901,237.81 248,396.30 5. Mobilization 6. Total Work Completed 901,237.81 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 896,237.81 243,396.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 243,396.30