Dept. of Trans. PROGRESS Serial No. Contract No. 18-234-13-35 03-1G0104 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 47% Location: Federal Project: 03-YUB-20-1.6/3.4 ACNH-P020(183) Progress payment No. 002 Payment period ending: 08-20-18 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 399,225.45 238,782.60 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 399,225.45 238,782.60 5. Mobilization 52,250.00 11,000.00 6. Total Work Completed 451,475.45 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 451,475.45 249,782.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,782.60