Dept. of Trans. PROGRESS Serial No. Contract No. 20-325-09-26 03-1G1504 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 88% Location: Federal Project: 03-NEV-80-58.8/58.8 NONE Progress payment No. 004 Payment period ending: 11-20-20 TPA CONSTRUCTION INC 2406 CLUBHOUSE DRIVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 531,752.00 282,127.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 531,752.00 282,127.00 5. Mobilization 35,000.00 1,750.00 6. Total Work Completed 566,752.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 566,752.00 283,877.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 283,877.00