Dept. of Trans. PROGRESS Serial No. Contract No. 20-262-12-11 03-1G6604 PROGRESS PAYMENT VOUCHER %complete: %time: 87% 90% Location: Federal Project: 03-BUT-162-12.6/15.6 NONE Progress payment No. 003 Payment period ending: 09-20-20 LAMON CONSTRUCTION CO INC 871 VON GELDERN WAY YUBA CITY CA 95991 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,466,068.29 144,301.80 2. a. Extra Work 204,196.21 10,268.67 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 2,670,264.50 154,570.47 5. Mobilization 6. Total Work Completed 2,670,264.50 7. Deductions -110,162.37 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,560,102.13 154,570.47 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,570.47