Dept. of Trans. PROGRESS Serial No. Contract No. 20-170-14-20 03-1G6704 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 62% Location: Federal Project: 03-GLE-162-54.0/65.3 ACST-S162(41) Progress payment No. 002 Payment period ending: 06-20-20 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,761,418.11 2,385,926.71 2. a. Extra Work b. Adustment Comp. -1,000.00 -1,000.00 3. Materials on Hand 4. Earned Subject to Retention 2,760,418.11 2,384,926.71 5. Mobilization 6. Total Work Completed 2,760,418.11 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,760,418.11 2,384,926.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,384,926.71