Dept. of Trans. PROGRESS Serial No. Contract No. 20-239-14-40 03-1G8204 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 20% Location: Federal Project: 03-YOL-505-0.3/3.6 NONE Progress payment No. 002 Payment period ending: 08-20-20 MORGAN CREEK CONSTRUCTION 20501 CHIPETA WAY REDDING CA 96003 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 101,715.70 36,788.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 101,715.70 36,788.00 5. Mobilization 6. Total Work Completed 101,715.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 101,715.70 36,788.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 36,788.00