Dept. of Trans. PROGRESS Serial No. Contract No. 26-054-06-41 03-1H1404 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 19% Location: Federal Project: 03-BUT-99-R3.1/5.0 ACNH-P099(690) Progress payment No. 012 Payment period ending: 02-20-26 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,031,321.97 492,738.13 2. a. Extra Work 429,760.85 128,325.54 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 9,461,082.82 621,063.67 5. Mobilization 1,130,000.00 56,500.00 6. Total Work Completed 10,591,082.82 7. Deductions -76,352.53 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,514,730.29 675,563.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 675,563.67