Dept. of Trans. PROGRESS Serial No. Contract No. 26-082-07-39 03-1H1404 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 24% Location: Federal Project: 03-BUT-99-R3.1/5.0 ACNH-P099(690) Progress payment No. 013 Payment period ending: 03-20-26 MARTIN BROTHERS CONSTRUCTION 8801 FOLSOM BLVD #260 SACRAMENTO CA 95826 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,731,309.32 699,987.35 2. a. Extra Work 483,929.83 54,168.98 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 10,215,239.15 754,156.33 5. Mobilization 1,130,000.00 0.00 6. Total Work Completed 11,345,239.15 7. Deductions -64,352.53 12,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,280,886.62 766,156.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 766,156.33