Dept. of Trans. PROGRESS Serial No. Contract No. 23-110-13-16 03-1H2404 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 1% Location: Federal Project: 03-PLA-49-2.2/2.4 SNHG-P049(186) Progress payment No. 003 Payment period ending: 04-20-23 LAMON CONSTRUCTION CO INC PO BOX 632 YUBA CITY CA 95992 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 140,065.92 7,964.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 119,098.39 0.00 4. Earned Subject to Retention 259,164.31 7,964.00 5. Mobilization 62,290.00 0.00 6. Total Work Completed 202,355.92 7. Deductions -1,000.00 2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 320,454.31 9,964.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,964.00