Dept. of Trans. PROGRESS Serial No. Contract No. 18-205-15-43 03-1H2604 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 95% Location: Federal Project: 03-NEV-80-18.3/19.3 NONE Progress payment No. 002 Payment period ending: 07-20-18 CENTRAL COAST FINANCIAL GROUP INC 393 MORNING STAR DR SONORA CA 95370 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 338,425.00 168,950.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 338,425.00 168,950.00 5. Mobilization 55,000.00 2,750.00 6. Total Work Completed 393,425.00 7. Deductions -13,948.50 -697.43 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 379,476.50 171,002.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 171,002.57