Dept. of Trans. PROGRESS Serial No. Contract No. 17-332-14-17 03-1H3204 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 78% Location: Federal Project: 03-BUT-99-R34.6/R34.9 HSNH-P099(611) Progress payment No. 003 Payment period ending: 11-20-17 KNIFE RIVER CONSTRUCTION 1764 SKYWAY CHICO CA 95928 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 738,847.05 99,492.00 2. a. Extra Work 15,182.05 15,182.05 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 754,029.10 114,674.05 5. Mobilization 6. Total Work Completed 754,029.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 754,029.10 114,674.05 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 114,674.05