Dept. of Trans. PROGRESS Serial No. Contract No. 18-113-15-46 03-1H3504 PROGRESS PAYMENT VOUCHER %complete: %time: 38% 32% Location: Federal Project: 03-YUB-20-1.2/1.3 NONE Progress payment No. 002 Payment period ending: 04-20-18 R&R HORN INC 13504 SKYPARK INDUSTRIAL AVE CHICO CA 95973 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 278,581.04 264,706.04 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 278,581.04 264,706.04 5. Mobilization 75,715.00 75,715.00 6. Total Work Completed 354,296.04 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 354,296.04 340,421.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 340,421.04