Dept. of Trans. PROGRESS Serial No. Contract No. 18-143-15-31 03-1H3504 PROGRESS PAYMENT VOUCHER %complete: %time: 76% 59% Location: Federal Project: 03-YUB-20-1.2/1.3 NONE Progress payment No. 003 Payment period ending: 05-20-18 R&R HORN INC 13504 SKYPARK INDUSTRIAL AVE CHICO CA 95973 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 613,813.48 335,232.44 2. a. Extra Work 26,470.60 26,470.60 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 640,284.08 361,703.04 5. Mobilization 79,700.00 3,985.00 6. Total Work Completed 719,984.08 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 719,984.08 365,688.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 365,688.04