Dept. of Trans. PROGRESS Serial No. Contract No. 18-172-12-07 03-1H3504 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 86% Location: Federal Project: 03-YUB-20-1.2/1.3 NONE Progress payment No. 004 Payment period ending: 06-20-18 R&R HORN INC 13504 SKYPARK INDUSTRIAL AVE CHICO CA 95973 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 773,742.00 159,928.52 2. a. Extra Work 27,245.57 774.97 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 800,987.57 160,703.49 5. Mobilization 79,700.00 0.00 6. Total Work Completed 880,687.57 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 880,687.57 160,703.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 160,703.49