Dept. of Trans. PROGRESS Serial No. Contract No. 19-263-15-08 03-1H6004 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 10% Location: Federal Project: 03-ED-193-22.9/24.3 ACST-P193(13) Progress payment No. 001 Payment period ending: 09-20-19 TIMBERWORKS PO BOX 1240 MOUNT SHASTA CA 96067 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 126,248.00 126,248.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 232,185.46 232,185.46 4. Earned Subject to Retention 358,433.46 358,433.46 5. Mobilization 260,250.00 260,250.00 6. Total Work Completed 386,498.00 7. Deductions -44,432.69 -44,432.69 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 574,250.77 574,250.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 574,250.77