Dept. of Trans. PROGRESS Serial No. Contract No. 20-175-14-19 03-1H6004 PROGRESS PAYMENT VOUCHER %complete: %time: 78% 89% Location: Federal Project: 03-ED-193-22.9/24.3 ACST-P193(13) Progress payment No. 008 Payment period ending: 06-20-20 TIMBERWORKS PO BOX 1240 MOUNT SHASTA CA 96067 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,010,754.18 491,272.52 2. a. Extra Work 7,304.03 2,731.92 b. Adustment Comp. 3. Materials on Hand 67,629.50 -67,629.50 4. Earned Subject to Retention 2,085,687.71 426,374.94 5. Mobilization 347,000.00 0.00 6. Total Work Completed 2,365,058.21 7. Deductions -59,243.59 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,373,444.12 426,374.94 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 426,374.94