Dept. of Trans. PROGRESS Serial No. Contract No. 17-207-13-07 03-1H6204 PROGRESS PAYMENT VOUCHER %complete: %time: 28% 45% Location: Federal Project: 03-YUB-999 NONE Progress payment No. 001 Payment period ending: 07-20-17 LEE CONTRACTORS AND CONSULTANTS INC 1978 EUCALYPTUS RD NIPOMO CA 93444 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 72,890.30 72,890.30 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 72,890.30 72,890.30 5. Mobilization 6. Total Work Completed 72,890.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 72,890.30 72,890.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 72,890.30