Dept. of Trans. PROGRESS Serial No. Contract No. 25-142-07-36 03-1H6304 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 41% Location: Federal Project: 03-SAC-99-12.7/16.3 ACNH-P099(683) Progress payment No. 014 Payment period ending: 05-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,248,132.72 684,120.19 2. a. Extra Work 450,058.47 0.00 b. Adustment Comp. 740,730.75 0.00 3. Materials on Hand 843,441.77 -327,380.38 4. Earned Subject to Retention 9,282,363.71 356,739.81 5. Mobilization 1,175,000.00 58,750.00 6. Total Work Completed 9,613,921.94 7. Deductions -5,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,452,363.71 414,489.81 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 414,489.81