Dept. of Trans. PROGRESS Serial No. Contract No. 25-170-06-44 03-1H6304 PROGRESS PAYMENT VOUCHER %complete: %time: 62% 45% Location: Federal Project: 03-SAC-99-12.7/16.3 ACNH-P099(683) Progress payment No. 015 Payment period ending: 06-20-25 O C JONES & SONS INC 1520 FOURTH ST BERKELEY CA 94710 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 8,730,946.88 1,482,814.17 2. a. Extra Work 450,058.47 0.00 b. Adustment Comp. 740,730.75 0.00 3. Materials on Hand 843,441.77 0.00 4. Earned Subject to Retention 10,765,177.87 1,482,814.17 5. Mobilization 1,175,000.00 0.00 6. Total Work Completed 11,096,736.10 7. Deductions -4,000.00 1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,936,177.87 1,483,814.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,483,814.17