Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 22-034-13-33 03-1H8204 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 98% Location: Federal Project: 03-SAC-50-15.8/23.1 NONE 03-ED-50-0.0/R1.9 Progress payment No. 008 Payment period ending: 01-20-22 ST FRANCIS ELECTRIC INC PO BOX 2057 SAN LEANDRO CA 94577 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,798,017.30 6,161.22 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,798,017.30 6,161.22 5. Mobilization 292,324.50 0.00 6. Total Work Completed 2,090,341.80 7. Deductions -9,500.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -137,449.63 -616.12 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,943,392.17 5,545.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,545.10