Dept. of Trans. PROGRESS Serial No. Contract No. 21-173-14-46 03-1H8704 PROGRESS PAYMENT VOUCHER %complete: %time: 27% 62% Location: Federal Project: 03-YOL-80 SNHG-P113(37) Progress payment No. 002 Payment period ending: 06-20-21 APEX FENCE CO INC PO BOX 545 ANDERSON CA 96007 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 492,590.63 481,290.63 2. a. Extra Work b. Adustment Comp. -3,000.00 -3,000.00 3. Materials on Hand 4. Earned Subject to Retention 489,590.63 478,290.63 5. Mobilization 19,000.00 19,000.00 6. Total Work Completed 508,590.63 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 508,590.63 497,290.63 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 497,290.63