Dept. of Trans. PROGRESS Serial No. Contract No. 25-080-09-23 03-1H9904 PROGRESS PAYMENT VOUCHER %complete: %time: 56% 50% Location: Federal Project: 03-PLA-80-68.3/69.7 ACIM-804(337) 03-NEV-80-0.0/R2.7 Progress payment No. 012 Payment period ending: 03-20-25 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 31,071,868.01 138,076.09 2. a. Extra Work 2,284,910.41 828,782.66 b. Adustment Comp. -87,579.61 0.00 3. Materials on Hand 570,302.41 -59,246.59 4. Earned Subject to Retention 33,839,501.22 907,612.16 5. Mobilization 6,855,000.00 342,750.00 6. Total Work Completed 40,124,198.81 7. Deductions -2,000.00 9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 40,692,501.22 1,259,362.16 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,259,362.16