Dept. of Trans. PROGRESS Serial No. Contract No. 24-345-09-43 03-1J0104 PROGRESS PAYMENT VOUCHER %complete: %time: 99% 95% Location: Federal Project: 03-VAR-999 HSNH-000C(540) Progress payment No. 007 Payment period ending: 11-20-24 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,089,542.91 81,478.06 2. a. Extra Work 35,055.30 27,795.30 b. Adustment Comp. -14,559.63 -14,559.63 3. Materials on Hand 4. Earned Subject to Retention 2,110,038.58 94,713.73 5. Mobilization 226,127.50 0.00 6. Total Work Completed 2,336,166.08 7. Deductions -6,238.70 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,329,927.38 94,713.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 94,713.73