Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 25-058-13-28 03-1J0104 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-VAR-999 HSNH-000C(540) Progress payment No. 008 Payment period ending: 11-27-24 CALIFORNIA HIGHWAY CONSTRUCTION GROUP INC 1647 WILLOW PASS RD #150 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,109,419.26 19,876.35 2. a. Extra Work 35,055.30 0.00 b. Adustment Comp. -7,856.61 6,703.02 3. Materials on Hand 4. Earned Subject to Retention 2,136,617.95 26,579.37 5. Mobilization 226,127.50 0.00 6. Total Work Completed 2,362,745.45 7. Deductions -30,000.00 -23,761.30 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,332,745.45 2,818.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,818.07