Dept. of Trans. PROGRESS Serial No. Contract No. 26-169-08-30 03-1J1704 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 13% Location: Federal Project: 03-PLA-89-13.0/21.6 ACST-S089(35) 03-NEV-89-0.0/0.6 Progress payment No. 002 Payment period ending: 06-20-26 TEICHERT CONSTRUCTION 3500 AMERICAN RIVER DRIVE SACRAMENTO CA 95864 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 469,294.70 454,669.69 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 469,294.70 454,669.69 5. Mobilization 6. Total Work Completed 469,294.70 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 469,294.70 454,669.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 454,669.69